Every New Year throughout Michigan brings more construction!  More yellow flashing lights!  More flaggers!  More detours!  Although there is added inconvenience, that is the price that we must pay to have good roads to drive on and the roads in Ogemaw County are the best around.  The following table is a preliminary list of construction projects and may change throughout the year.


WK  
This section will be updated frequently to notify the public of construction projects and road closures in Ogemaw County.  These times are only preliminary and are subject to change without notice.  Every attempt will be made to update this page when the schedule changes.  All 911, Emergency and other pertinent authorities are notified prior to the closure of a public road.  

Roads that are closed due to reconstruction are still open to residents and businesses located within the reconstruction limits.  Every attempt will be made to provide a passable road to residents and businesses within the project limits, however, the Road Commission will not be responsible for damage caused to vehicles due to the reconstruction project.
WK3    

2012 Tentative Road Reconstruction Schedule
L/P Township Road Limits Length Start Finish
L
Cumming / Hill Wiltse Road Curve south 1.00 4-June 27-July
L Hill Wiltse Road Brady Road east 0.50 4-June 27-July
L Churchill Peterson Road M-55 south 1.57 30-July 14-Sept
P Klacking Sage Lake Road Fairview Road east 1.00 17- Sept 26-Oct
       
 
Paving Gravels
L/P Township Road Limits Length Start Finish
L
Klacking / West Branch Peters Road Campbell Road to Mud Lake Road 1.00    
L Churchill Boughner Lake Road Hardwood Heights Road north 1.40    

Funded Projects
L/P Township Road Limits Length Start Finish
P
Logan State Road Sage Lake Road to Clark Road - Paving 1.00 6-June 24-June
P Churchill State Road M-33 east to Morrison Road - Bituminous Reconstruction 1.00 9-July 3-Aug